CO129-309 - Public Offices & Others - 1901 — Page 552

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All AI Reviewed

547

18. Even if a lump sum contract is agreed upon, a schedule of rates should be attached to the specification and referred to in the agreement, so that any extra work may be measured up and paid for at fixed rates. Unless this is done, claims for extra work may be a cause of troublesome disputes.

19. A further defect of the lump sum contract is that it commits the Engineer irrevocably to his original design and renders it very difficult to introduce any improvement which may occur to him during construction.

20. The schedule of rates contract is the system which should be used in all but a few exceptional cases. It gives the utmost freedom to the Engineer to adapt his construction to the exigencies of the case as revealed during construction, and is therefore specially applicable to such works as the construction of sewers, where it is impossible to predict the nature of the soil or to say what steps must be taken to deal with existing sewers and drains. It affords also a most valuable insight into the detailed cost of works.

21. The books and forms required for this system of accounts are as follows:-

For Contract work

1. Measurement book,

2. Contractors certificate book,

3. Contractors certificate form.

For Departmental work

4. Morning report,

5. Figured Abstract,

6. Paysheet.

22. The measurement book is simply a calculation book in which the Engineer enters the measurements made on the ground and calculates out the quantities, such as the cubic yards of excavations and so forth.

23. The quantities obtained in the measurement book are inscribed

(4)

C.3.D 72 g 1970.6.

Edit History

2026-06-01 06:56:21 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
547 18. Even if a lump sum contract is agreed upon, a schedule of rates should be attached to the specification and referred to in the agreement, so that any extra work may be measured up and paid for at fixed rates. Unless this is done, claims for extra work may be a cause of troublesome disputes. 19. A further defect of the lump sum contract is that it commits the Engineer irrevocably to his original design and renders it very difficult to introduce any improvement which may occur to him during construction. 20. The schedule of rates contract is the system which should be used in all but a few exceptional cases. It gives the utmost freedom to the Engineer to adapt his construction to the exigencies of the case as revealed during construction, and is therefore specially applicable to such works as the construction of sewers, where it is impossible to predict the nature of the soil or to say what steps must be taken to deal with existing sewers and drains. It affords also a most valuable insight into the detailed cost of works. 21. The books and forms required for this system of accounts are as follows:- For Contract work 1. Measurement book, 2. Contractors certificate book, 3. Contractors certificate form. For Departmental work 4. Morning report, 5. Figured Abstract, 6. Paysheet. 22. The measurement book is simply a calculation book in which the Engineer enters the measurements made on the ground and calculates out the quantities, such as the cubic yards of excavations and so forth. 23. The quantities obtained in the measurement book are inscribed (4) C.3.D 72 g 1970.6.
Baseline (Original)
547 18. Even if a lump sum contract is agreed upon a schedule of rates should be attached to the specification and referred to in the agreement, so that any extra work may be measured up and paid for at fixed rates. Unless this is done claims for extra work may be a cause of troublesome disputes. 19. A further defect of the lump sum contract is that it commits the Engineer irrevocably to his original design and renders it very difficult to introduce any improvement which may occur to him during construction. 20. The schedule of rates contract is the system which should be used in all but a few exceptional cases. It gives the utmost freedom to the Engineer to adapt his construction to the exi- gencies of the case as revealed during construction, and is there fore specially applicable to such works as the construction of sewers, where it is impossible to predict the nature of the soil or to say what steps must be taken to deal with existing sewers and drains. It affords also a most valuable insight into the detailed cost of works. 21. The books and forms required for this system of accounts are as follows:- For Contract work 1.Measurement book, 2. Contractors certificate book, 3. Contractors certificate form. For Departmental work 4. Morning report, 5. Figured Abstract, 6. Paysheet. 22. The measurement book is simply a calculation book in which the Engineer enters the measurements made on the ground and calculates out the quantities. The cubic yards of excavations and so forth. 23. The quantities obtained in the measurement book are inscribed (4) C.3.D 72 g 1970.6.
2026-06-01 06:56:21 · Baseline
View content

547

18. Even if a lump sum contract is agreed upon a schedule of rates should be attached to the specification and referred to in the agreement, so that any extra work may be measured up and paid for at fixed rates. Unless this is done claims for extra

work may be a cause of troublesome disputes.

19. A further defect of the lump sum contract is that it commits the Engineer irrevocably to his original design and renders it very difficult to introduce any improvement which may

occur to him during construction.

20.

The schedule of rates contract is the system which should be used in all but a few exceptional cases. It gives the utmost freedom to the Engineer to adapt his construction to the exi- gencies of the case as revealed during construction, and is there fore specially applicable to such works as the construction of sewers, where it is impossible to predict the nature of the soil or to say what steps must be taken to deal with existing sewers and drains. It affords also a most valuable insight into the

detailed cost of works.

21. The books and forms required for this system of accounts

are as follows:-

For Contract work

1.Measurement book,

2.

Contractors certificate book,

3. Contractors certificate form.

For Departmental work

4. Morning report,

5. Figured Abstract, 6. Paysheet.

22. The measurement book is simply a calculation book in which the Engineer enters the measurements made on the ground and calculates out the quantities. The cubic yards of excavations

and so forth.

23. The quantities obtained in the measurement book are

inscribed

(4)

C.3.D 72 g 1970.6.

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.